KCMO had a significant water main break on the mill and overlay project on State Line.
Prairie Village Public Works is working with them on whether their contractor patches the roadway or they want PV to… Just a coordination issue to make sure it’s right before the surface goes down.
Unfortunately this will delay efforts for paving this week and pushes the paving into next week.

Next week’s TUESDAY City Council agenda should be coming out soon.